June 5, 2013 Working Group 2: Aquatic Resources, Terrestial, Wetlands, Riparian Resources Meeting Presentation |
06/05/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Karl Meyer Comments on FirstLight Hydro Generating Company's Revised Study Plan (RSP) |
08/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Karl Meyer Comments on FirstLight Hydro Generating Company's Updated Proposed Study Plan (PSP) |
07/14/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Landowners & Concerned Citizens for License Compliance (LCCLC) Comments on proposed Relicensing of Turner Falls and Northfield Mountain |
01/30/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Letter FirstLight filing Phase IB and Phase II Reports for Archaeological Investigations in Vermont, New Hampshire, and Massachusetts as part of Relicensing Study No. 3.7.1 |
12/14/2018 |
Cultural |
Download
|
Letter from FirstLight pertaining to the causation study (Study No. 3.1.2) |
08/12/2014 |
Geology and Soils |
Download
|
Letter from FirstLight regarding Study No. 3.3.6 Impact of Project Operations on Shad Spawning, Spawning Habitat and Egg Deposition in the Area of the Northfield Mountain and Turners Falls Project. |
08/25/2014 |
Fish and Aquatics |
Download
|
Letter from FirstLight Re: Study No. 3.3.18- Impact of Turners Falls Canal Drawdown on Fish Migration and Aquatic Organisms |
08/15/2014 |
Fish and Aquatics |
Download
|
Letter of Support for USFWS EOT by the New Hampshire Department of Environmental Services and request for extension of time to Comment on Draft Proposed Study Plans |
06/18/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Letter to FERC from Connecticut River Residents concerning Northfield Mountain and Turners Falls Dam licensing issues |
02/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Letter to FirstLight Hydro Generating Company re the Interim ILP schedule for Study Plan Determination for the Turners Falls Project |
12/13/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Letter to Peter Champoux from FERC responding to the 3/1/13 letter and the 6/19/13 email discussing the parcel of land that abuts the power canal wall of the Turners Falls Project under P-1889 |
06/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
MADFW Additional Comment/Supplemental Information re: Documented Presence of State-listed Mussel Species in the Project Area |
03/13/2014 |
Fish and Aquatics |
Download
|
MA Division of Fisheries and Wildlife Comments on Technical Meeting (11/25/13) re:Effects of Decommissioning the Vermont Yankee Power Plant on Revised Proposed Study Plan |
12/06/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
March 16, 2016, Study Meeting Summary. |
03/31/2016 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Department of Conservation and Recreation Comments on Revised Study Plans |
08/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Department of Environmental Protection Comments on Revised Study Plans |
08/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Department of Environmental Protection comments to Proposed Study Plans under P-1889 |
07/12/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Division of Fisheries and Wildlife Comments in regard to Extension of time request by the US Fish and Wildlife Service to Comment on Proposed Study Plans |
06/17/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Division of Fisheries and Wildlife Comments on Northfield Mountain and Turners Falls Revised Proposed Study Plan |
08/29/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Division of Fisheries and Wildlife Comments on Updated Proposed Study Plan |
07/12/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Division of Fisheries and Wildlife (MADFW) Impacts of Closure of Vermont Yankee Nuclear Power Plant on Results of Proposed Study Plans |
08/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Historical Commission Comments on the Revised Proposed Study Plan |
08/26/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Historical Commission comments to assist in compliance with Section 106 of the National Historic Preservation Act oof 1966 as amended (36 CFR 800). |
01/16/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Historical Commission (MHC) submits letter to FERC: concurs with FERC's determination of the project APE |
12/19/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Historical Commission submits Comments on Updated Proposed Study Plan 3.7.1 |
07/16/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Historical Commission submits comments re the proposed study plan for the relicensing of the Turners Falls and Northfield Mountain Pumped Storage Hydroelectric |
04/24/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
May 14, 2013 Broad Overview of All Proposed Studies Meeting Presentation |
05/14/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
May 14 (afternoon) and May 15, 2013 Working Group 1 (Geology and Soils, Water Resources, Developmental Resources) Meeting Presentation |
05/14/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
May 21, 2013 Working Group 2: Aquatic Resources, Terrestial, Wetlands, Riparian Resources Meeting Presentation |
05/21/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
May 22, 2013 Working Group 2: Aquatic Resources, Terrestial, Wetlands, Riparian Resources Meeting Presentation |
05/22/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Modification to Integrated Licensing Process Schedule |
12/21/2012 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
National Marine Fisheries Service Comments on Updated Proposed Study Plans |
07/15/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
National Oceanic and Atmospheric Administration (NOAA) Fisheries comments on Revised Study Plans |
08/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
National Park Service, Northeast Region comments on Proposed Study Plans Revision |
07/14/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New England Farmers Union review of Pre-Application Documents |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New England Flow and American Whitewater's Comments and Study Requests |
01/30/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
NEW ENGLAND FLOW Comments on Updated Proposed Study Plans |
07/09/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New Hampshire Department of Environmental Services Comments on Pre-Application Documents and Study Requests for 5 Hydroelectric Projects on the Connecticut River |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New Hampshire Department of Environmental Services (NHDES) Comments on Revised Study Plan for FERC NO. 1889 (Turners Falls) and 2485 (Northfield Mountain) |
08/29/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New Hampshire Department of Environmental Services (NHDES) Comments on Updated Proposed Study Plan |
07/15/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New Hampshire Department of Fish and Game comments to Draft Proposed Study Plans |
07/11/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New Hampshire Fish and Game Department Comments on Impacts of Closure of Vermont Yankee Nuclear Power Plant on Results of Proposed Study Plans |
08/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
NFM AFLA Volume 1 of 5 |
12/04/2020 |
Amended Final License Application |
Download
|
NMFS Study Requests and Comments regarding PAD |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
NOAA Fisheries comments in support for US Fish and Wildlife Service Extension of Time request on P-1889 Turners Falls and P-2485 Northfield Mtn Pump Storage |
06/17/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Nolumbeka Project, Inc. Traditional Cultural Properties Study Request |
07/14/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Northfield Conservation Commission, Town of Northfield, MA submits Comments re Northfield Mountain Pumped Storage Project |
02/22/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Northfield Mountain Generation Station CFD Modeling for Fish Exclusion Net Forces Report |
06/01/2019 |
Fish and Aquatics |
Download
|
Northrop, Devine and Tarbell, Inc.. 1991. Connecticut River Riverbank Management Master Plan (Draft). Northeast Utilities Service Company, Inc. |
01/01/1991 |
Geology and Soils |
Download
|