FERC Order approving report on existing uses and occupancies of project lands and waters re FirstLight Hydro Generating Company |
05/13/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FERC Public Files Memo: Initial Tribal consultation meeting with the Narragansett Indian Tribe of Rhode Island |
05/03/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Massachusetts Historical Commission submits comments re the proposed study plan for the relicensing of the Turners Falls and Northfield Mountain Pumped Storage Hydroelectric |
04/24/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Scoping Document 2 for the Wilder (FERC No. 1892-026), Bellows Falls (FERC No. 1855-045), Vernon (FERC No. 1904-073), and Turners Falls (FERC No. 1889-081) hydroelectric projects, and the Northfield Mountain Pumped Storage Project (FERC No. 2485-063) |
04/15/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments from Stanley Johnson of River Residents Association regarding the Turner Falls and Northfield Projects |
02/16/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments from Robert and Linda Emond of River Residents Association, Connecticut River concerns regarding the Turner Falls and Northfield Projects |
02/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments from Robert Stafford and Family of River Residents Association, Connecticut River concerns regarding the Turner Falls and Northfield Projects |
02/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Northfield Conservation Commission, Town of Northfield, MA submits Comments re Northfield Mountain Pumped Storage Project |
02/22/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments from Michael and Diane Kane of River Residents Association, Connecticut River concerns regarding the Turner Falls and Northfield Projects |
02/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments from Cynthia S. Dale of River Residents Association Connecticut River concerns regarding the Turner Falls Project and Northfield Mountain Projects |
02/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Stefanie Krug Additional information and comments letter for study request (Accession No. 20130301-5029) |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
ILP Comments or Study Request of Massachusetts Department of Environmental Protection |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
ILP Comments or Study Request of U.S. Fish and Wildlife Service/New England Field Office |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments of Joanne McGee regarding Canoe/Kayaks access on Connecticut River |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments and Study Requests of Kurt Heidinger for Biocitizen School of Environmental Philosophy and Practice |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments from Peter W. Conway of River Residents Association re regarding the Turner Falls Project and Northfield Mountain Projects |
02/16/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments of Four Star Farms, Inc. re the Northfield Mountain Relicensing |
02/20/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New England Farmers Union review of Pre-Application Documents |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Study Requests of Deerfield River Trout Unlimited |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Connecticut River Joint Commissions Comments on Integrated Licensing Process and Study Request for FERC project numbers P-1904 (Vernon), P-1855 (Bellows Falls), P-1892 (Wilder), 1889 (Turners Falls), No. 2485 (Northfield Mountain). |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
The Vermont Agency of Natural Resources (Agency) submits comments and requests for studies. |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
New Hampshire Department of Environmental Services Comments on Pre-Application Documents and Study Requests for 5 Hydroelectric Projects on the Connecticut River |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
The Nature Conservancy Comments on Scoping Document 1 and Study Requests for the Wilder, Bellows Falls (FERC No. 1855-045), Vernon (FERC No. 1904-073), and Turners Falls (FERC No. 1889-081) hydroelectric projects, and the Northfield Mountain Pumped Storag |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comment of Howard Fairman re environmental impacts on migratory fish in relicensing of Northfield Mountain Pumped Storage. |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments on Connecticut River Massachusetts water withdrawal by Massachusetts Farm Bureau Federation ( A. Richard Bonanno, Ph.D.) |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments on the PAD, Scoping Document 1, and Study Requests of Connecticut River Watershed Council, Inc. |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Stefanie Krug Study Plan Request for the Northfield Mountain Trail Assessment under P-2485: Mountain Bike Trails Access |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments and Study Request submitted by The Nolumbeka Project, Inc, et al |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FERC Letter to FirstLight Hydro Generating Company providing Identified PAD Deficiencies, Additional Information Requests, and Study Requests |
03/01/2013 |
Pre-Application Document |
Download
|
Comments from Leena Newcomb of the River Residents Association re the Turners Falls Project |
02/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Photos from Anonymous River Resident regarding the Turner Falls and Northfield Projects |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments of Chris Curtis re the Turners Falls Project Article from The Recorder: "Lower water hampers use of Connecticut River, Jeopardizes potential river rescue response." |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments of Thomas Shearer et al re the Northfield Mountain Pumped Storage Project |
01/31/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments from Leena Newcomb of River Residents Association regarding the Turner Falls Project and Northfield Mountain Projects |
01/31/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comment and Study Requests of New England FLOW, American Whitewater and Appalachian Mountain Club |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments on Scoping Document 1 for the Wilder, Bellows Falls, Vernon and Turners Falls hydroelectric projects, and the Northfield Mountain Pumped Storage Project from Northeast Climate Science Center |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
NMFS Study Requests and Comments regarding PAD |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Supplemental Information of Vivien Venskowski of The River Residents Association. Connecticut River concerns on Extreme Water Level Fluctuations and Campsite License Terms |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments on PAD, SD1 and Study Requests from Franklin Conservation District |
03/01/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments on the Preliminary Application Document, Scoping Document 1, and Study Requests submitted by Franklin Regional Council of Governments |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
SD1 Comments, PAD Comments, and Study Requests of the Massachusetts Division of Fisheries and Wildlife (MADFW) |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments on the Preliminary Application Document, Scoping Document 1, and Study Requests submitted by the Landowners and Concerned Citizens for License Compliance |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments on the Preliminary Application Document, Scoping Document 1, and Study Requests submitted by the Town of Gill, MA Select Board and Conservation Commission |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Letter to FERC from Connecticut River Residents concerning Northfield Mountain and Turners Falls Dam licensing issues |
02/25/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Supplemental/Additional Information Response to Data Request of Town of Montague, MA, Native American Cultural Landscape District Properties in Turners Falls Management Plan |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Appalachian Mountain Club, Vermont River Conservancy, and Friends |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Comments and Study Requests in Response to the Notice of Intent to File License Application, Filing of Pre-Application Document (PAD), Commencement of Pre-Filing Process and Scoping and Request for Comments on the PAD and Scoping Document |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Transcript of 1/31/13 scoping meeting held in Turners Falls, Massachusetts for the Connecticut River Projects' Cumulative Effects re TransCanada Hydro Northeast, Inc and FirstLight Hydro Generating Company |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Transcript of 1/31/13 scoping meeting held in Turners Falls, Massachusetts for the Northfield Mountain and Turners Falls Hydroelectric Projects re FirstLight Hydro Generating Company |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Transcript of 1/30/13 scoping meeting held in Turners Falls, Massachusetts for the Vernon, Northfield Mountain, and Turners Falls Hydroelectric Projects re TransCanada Hydro Northeast, Inc and FirstLight Hydro Generating Company |
02/28/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|