FirstLight - March 8, 2016 Study 3.3.2 Adult Shad Telemetry Data Analysis Meeting. Presentation. |
03/08/2016 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.8 Computation Fluid Dynamics Modeling in the Vicinity of the Fishway Entrances and Powerhouse Forebays |
09/14/2015 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.6 Impact of Project Operations on Shad Spawning, Spawning Habitat and Egg Deposition in the area of Northfield Mountain and Turner Falls Projects |
09/14/2015 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.5 Evaluate Downstream Passage of American Eel |
09/14/2015 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.16 Habitat Assessment, Surveys, and Modeling of Suitable Habitat for State-Listed Mussel Species in the Connecticut River Below Cabot Station |
09/14/2015 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.3 Evaluate Downstream Passage of Juvenile American Shad |
09/14/2015 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.12 Evaluate Frequency and Impact of Emergency Water Control Gate Discharge Events and Bypass Flume Events on Shortnose Sturgeon Spawning and Rearing Habitat in the Tailrace and Downstream From Cabot Station |
09/14/2015 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.13 Impacts of the Turner Falls Project and Northfield Mountain Project on Littoral Zone Fish Habitat and Spawning Habitat |
09/14/2015 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.2 Evaluate Upstream and Downstream Passage Addendum 1 |
05/01/2017 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.15 Assessment of Adult Sea Lamprey Spawning with the Turner Falls Project and Northfield Mountain Project Area |
09/14/2015 |
Fish and Aquatics |
Download
|
FirstLight files Turners Falls Project - Fish Passage Facilities 2013 Annual Report of Operations |
03/15/2014 |
Fish and Aquatics |
Download
|
Letter from FirstLight Re: Study No. 3.3.18- Impact of Turners Falls Canal Drawdown on Fish Migration and Aquatic Organisms |
08/15/2014 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.3 Evaluate Downstream Pass Evaluate Downstream Pass Evaluate Downstream Passage Addendum 1 |
05/01/2017 |
Fish and Aquatics |
Download
|
FirstLight Proposed Modification to Study Plan 3.3.2 Evaluate Upstream and Downstream Passage of Adult American Shad |
12/08/2014 |
Fish and Aquatics |
Download
|
FERC Memo: FERC Staff Memo to Public Records documenting telephone conversation between Commission staff and Dr. Theodore Castro-Santos of the U.S. Geological Survey’s S.O. Conte Anadromous Fish Research Center |
02/03/2014 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.5 Evaluate Downstream Passage of American Eel |
03/01/2017 |
Fish and Aquatics |
Download
|
Letter from FirstLight regarding Study No. 3.3.6 Impact of Project Operations on Shad Spawning, Spawning Habitat and Egg Deposition in the Area of the Northfield Mountain and Turners Falls Project. |
08/25/2014 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.19 Evaluate the Use of an Ultrasound Array to Facilitate Upstream Movement to Turners Falls Dam by avoiding Cabot Station Tailrace -2018 Study Report |
03/01/2019 |
Fish and Aquatics |
Download
|
Relicensing Study Report 3.3.1 Instream Flow Habitat Assessments in the Bypass Reach and Below Cabot Station Addendum 1 (Attachment D2) |
04/01/2017 |
Fish and Aquatics |
Download
|
Relicensing Study Report 3.3.1 Instream Flow Habitat Assessments in the Bypass Reach and Below Cabot Station Addendum 1 |
04/01/2017 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.15 Assessment of Sea Lamprey Spawning within Assessment of Sea Lamprey Spawning within Turners Falls Turners Falls Project Northfield Mountain Project Area Addendum 1 Impact on Sea Lamprey Spawning Nests near Stebbins Island |
05/01/2018 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.20 Ichthyoplankton Entrainment Assessment at Northfield Mountain Project -Second year |
12/01/2016 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.4 Evaluate Upstream Passage of American Eel at the Turner Falls Project |
03/31/2015 |
Fish and Aquatics |
Download
|
2014 Initial Study Report. Summary Study 3.3.19. |
09/15/2014 |
Fish and Aquatics |
Download
|
Relicensing Study 3.3.13 Impacts of the Turners Falls Project and Northfield Mountain Project on Littoral Zone Fish Habitat and Spawning Habitat Study Report |
06/30/2016 |
Fish and Aquatics |
Download
|
Relicensing Study Report 3.3.1 Instream Flow Habitat Assessments in the Bypass Reach and Below Cabot Station Addendum 1 (Attachment D4) |
04/01/2017 |
Fish and Aquatics |
Download
|
Updated Study Report Summary 3.3.4 Evaluate Upstream Passage of American Eel at the Turner Falls Project |
09/14/2015 |
Fish and Aquatics |
Download
|
Udated Study Report Summary 3.3.9 Two-Dimensional Modeling of the Northfield Mountain Pumped Storage Project Intake/Tailrace Channel and Connecticut River Upstream and Downstream of the Intake/Tailrace |
09/14/2015 |
Fish and Aquatics |
Download
|
Final License Application Exhibit G |
04/29/2016 |
Final License Application |
Download
|
Final License Application Initial Statement and Additional Information |
04/29/2016 |
Final License Application |
Download
|
Final License Application Exhibit C |
04/29/2016 |
Final License Application |
Download
|
Final License Application Exhibit A |
04/29/2016 |
Final License Application |
Download
|
Final License Application Exhibit E |
04/29/2016 |
Final License Application |
Download
|
Final License Application Exhibit H |
04/29/2016 |
Final License Application |
Download
|
Final License Application Exhibit D |
04/29/2016 |
Final License Application |
Download
|
Final License Application Exhibit B |
04/29/2016 |
Final License Application |
Download
|
Final License Application Cover Letter |
04/29/2016 |
Final License Application |
Download
|
June 11-12, 2013 Working Group 3: Recreation and Land Use Resources, Aesthetic Resources , Cultural Resources Meeting Presentation |
06/10/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FirstLight Hydro Generating Company files Notification of Dates and Agenda for 2014 Initial Study Report Meeting |
08/21/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Proposed Study Plan (PSP) for the relicensing of the Turners Falls Project and Northfield Mountain Project (Volume 2 Appendix A) |
04/15/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
June 5, 2013 Working Group 2: Aquatic Resources, Terrestial, Wetlands, Riparian Resources Meeting Presentation |
06/05/2013 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FERC Meeting Memo. FWS Formal Dispute Resolution. Meeting between Commission staff, the U.S. Fish and Wildlife Service (FWS) and FirstLight Hydro Generating Company (FirstLight) on the FWS’s formal dispute filed on March 13, 2014 |
04/16/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FERC Letter requesting the Dispute Resolution Panel to provide recommendation by 5/2/14 re the Suspension of Dispute Resolution Panel |
05/02/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
USDOI/Fish and Wildlife Service/NEFO Submits ILP Proposed Study Plan or Revised Study under P-2485. |
05/02/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
Supplemental Information from USDOI/Fish and Wildlife Service/NEFO re: Submitted ILP Proposed Study Plan or Revised Study under P-2485. |
05/02/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FirstLight Letter Supplemental/Additional Information to FERC re USFWS Proposed Revised Study Plan |
05/02/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FERC Staff Memo: Telephone conference 5/6/2014 between Commission Staff, Massachusetts Division of Fisheries and Wildlife, and FirstLight Hydro Generating Company |
05/07/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FERC Resolution of Dispute on Entrainment Study, and Clarification on Study 3.1.2 |
09/03/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FirstLight Hydro Generating Company files 2014 Study Progress Report |
07/23/2014 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|
FirstLight Response to Stakeholder Requests for Study Modifications and/or New Studies Based on the Study Report and Meeting Summary (5/31/2016) |
05/31/2016 |
FERC Scoping/Integrated Licensing Process (ILP) Process |
Download
|